Home / Services / ADU Construction

ADU Construction in the East Bay

A second unit on your lot, permitted properly.

Detached backyard ADU with board-and-batten siding and glass doors, East Bay ADU construction
ADU Construction by NorCal Construction — CSLB licence #959458.

California changed its ADU laws substantially over the last several years, and the practical result is that building a second unit on a single-family lot went from nearly impossible to genuinely achievable in most of the cities we serve. We have built a steady stream of them since.

An ADU is still a house, though. It needs a foundation, a full set of systems, its own utilities and its own address, and it goes through plan check like any other building. Anyone quoting you an ADU as though it were a large shed has not built one.

Types of ADU We Build

Which type is right depends far more on your lot and your sewer lateral than on preference.

What an ADU Costs

ADU cost is dominated by three things: size, whether utilities have to be trenched a long way, and site access for equipment. Finishes matter far less. These are typical East Bay and North Bay ranges for planning.

Project scopeWhat it coversTypical range
Junior ADU (JADU)Up to 500 sq ft carved from the existing house, kitchenette, often shared bath.$90,000 – $160,000
Garage conversion ADUExisting structure converted, kitchen and bath added, separate entrance.$120,000 – $220,000
Attached ADUNew construction sharing a wall with the house. Shorter utility runs.$200,000 – $350,000
Detached new-build ADUStandalone unit, own foundation and systems. Per sq ft: $400–$600.$250,000 – $500,000 +

Market ranges for planning, not a quote. Your estimate depends on scope, materials and site conditions. Get a written line-item estimate.

The Hidden Costs Nobody Quotes

The build cost of an ADU is reasonably predictable. What varies enormously — and what separates a realistic estimate from a lowball one — is everything around it.

Utility trenching. Water, sewer, gas and electrical have to reach the unit. If your detached ADU is eighty feet from the house across a mature garden with a concrete driveway in between, that trench is a real line item.

The sewer lateral. Waste has to run to the main lateral at the correct slope. On a flat lot with the ADU downhill of the stack, easy. On a lot that falls the wrong way, you may need a pump system.

Electrical service. A second dwelling often pushes the property past what the existing service can carry, which means a service upgrade and coordination with the utility — that has its own calendar, independent of your builder.

Site access. A detached ADU behind a house with a narrow side yard means material gets carried, not driven, and sometimes craned. It is not a small difference.

We check all four before we give you a number, which is why our estimate takes a site visit rather than a phone call.

Project scopeWhat it coversTypical range
Junior ADU (JADU)Up to 500 sq ft carved from the existing house, kitchenette, often shared bath.$90,000 – $160,000
Garage conversion ADUExisting structure converted, kitchen and bath added, separate entrance.$120,000 – $220,000
Attached ADUNew construction sharing a wall with the house. Shorter utility runs.$200,000 – $350,000
Detached new-build ADUStandalone unit, own foundation and systems. Per sq ft: $400–$600.$250,000 – $500,000 +

Market ranges for planning, not a quote. Your estimate depends on scope, materials and site conditions. Get a written line-item estimate.

The Permit Path for an ADU

State law sets a framework, and cities apply it locally. In broad strokes: measured site plan and design, then structural and Title 24, then submittal, then plan check corrections, then issue. California law caps how long an agency may take to act on a complete ADU application, which has genuinely improved timelines — but plan-check corrections still take as long as they take.

Requirements you should expect to encounter: setbacks from the rear and side property lines, height limits that depend on whether the unit is detached and how close it sits to the boundary, separate address assignment, and solar requirements for new construction in many cases. Fire sprinklers may be required depending on whether the main house has them.

We handle the submittal and the corrections. What we will not do is promise you a timeline the city has not given us.

How Long an ADU Takes

PhaseTypical duration
Feasibility, survey and design6 – 12 weeks
Engineering and Title 243 – 6 weeks
Permit submittal and plan check2 – 5 months
Site work, utilities and foundation4 – 8 weeks
Framing, roof and weatherproofing4 – 6 weeks
Rough-in, insulation, drywall, finishes8 – 14 weeks
Typical time on site5 – 8 months

Is an ADU Worth It?

That depends on why you are building it, and the honest answer differs.

For rental income, the arithmetic is straightforward: build cost against realistic local rent for the unit size, minus vacancy, maintenance and the tax treatment your accountant will explain better than we can. In most of the cities we serve the payback period is long but the asset is real, and the unit continues to exist after it has paid for itself.

For housing family — an ageing parent, an adult child, a carer — the calculation is different and usually more favourable, because the alternative is an assisted-living cost or a second mortgage somewhere else.

For resale value, an ADU generally adds value, but not always the full build cost, and appraisal practice varies. We would not build one purely as a flip.

ADUs on Local Lots

Flat, generous lots in Concord, Pleasant Hill, Antioch and parts of Hayward are the easiest ADU sites we work on — room to place the unit, straightforward access, short utility runs. Those are the projects that come in closest to estimate.

Berkeley and El Cerrito lots are typically narrower and deeper, with mature planting and tight side yards, which raises access cost and often pushes the design taller rather than wider. Hillside parcels in the Oakland Hills and San Rafael need geotechnical input and engineered drainage, and in the hills wildfire-resistant construction requirements apply to the exterior assembly.

Questions we get asked

ADU Construction — Frequently Asked Questions

A detached new-build ADU generally runs $400–$600 per square foot in this market, putting a 600 sq ft unit somewhere between $250,000 and $360,000. Garage conversion ADUs are considerably cheaper, typically $120,000–$220,000, because the shell already exists.

Realistically nine months to a year and a half from first call to final inspection: roughly two to four months for design and engineering, two to five months in plan check, and five to eight months on site.

In California, ADUs can generally be rented long-term. Short-term rental rules are set by individual cities and vary a great deal, so confirm locally before you build a plan around that income.

Frequently not, particularly near transit, but it depends on your parcel and city. We confirm the requirement for your specific address during feasibility.

A JADU is up to 500 square feet created within the existing house — often a converted bedroom or a portion of the ground floor. It needs an exterior entrance and a kitchenette, and it can share a bathroom with the main house. It is the cheapest legal route to a second unit.

The ADU itself is typically assessed and added to your assessment; the existing house is generally not reassessed as a result. Your county assessor and your accountant are the right people to confirm the numbers for your situation.

Other services

We Also Build

Remodeled kitchen with dark cabinetry and a lit marble backsplash, kitchen remodeling by NorCal Construction

Kitchen Remodeling

Custom cabinetry, counters, islands and full layout changes, including moving plumbing and electrical where the layout calls for it.

Remodeled walk-in shower with dark stone tile and a glass enclosure, bathroom remodeling in the East Bay

Bathroom Remodeling

Tub-to-shower conversions, primary suites, guest baths and waterproofing done properly, not just prettily.

New home addition with grey siding and tall windows, built by NorCal Construction

Home Additions

Room additions, second storeys and bump-outs — engineered and framed to match the existing house instead of looking bolted on.

Garage conversion in progress with new white shaker cabinets and finished walls

Garage Conversions

Turn an under-used garage into a legal bedroom, office, gym or income-producing studio — permitted, insulated and finished.

Brick two-storey home with a covered front porch after a whole-home renovation

Whole-Home Renovations

Full-house renovations — systems, structure and finishes handled under one contract and one schedule.

Thinking about ADU construction?

Send us the details and we will come out, measure and put a written line-item estimate in your hands.